Richard HallerNY hit pause on large data centers. A massive project in Massena may be exempt

Over the past year, a proposed data center project has been the center of a tense community debate in Massena.

New York Digital Investment Group (NYDIG) and its affiliate cryptocurrency operators, North Country Collocation Services (NCCS), want to build a 1.5 million-square-foot, 635-megawatt data center near the St. Lawrence River. That equals around 70% of the power produced at the huge Moses Saunders hydroelectric dam nearby. If approved, it would be one of the largest data centers in New York State. 

Close access to this hydropower has made Massena an ideal location for data center developers. This project is planned for the shuttered Alcoa East/Reynolds industrial site. The company’s website says initial construction is slated for later this year. 

Earlier this year, Gov. Kathy Hochul signed an executive order temporarily restricting development of new hyperscale data centers exceeding 50 megawatts. These facilities used to power A.I. are controversial across the country. The moratorium gives state agencies more time to assess their impact. 

But the Massena project could be exempt from this statewide restriction. 

That’s because the moratorium isn’t a blanket ban on new data centers. It orders the DEC not to issue any new discretionary permits. But Massena officials say NCCS doesn’t require additional permits because it already applied for them back in 2020. 

Jason Pfotenhauer, director of St. Lawrence County’s Planning Office, said that NCCS’s exemption could be legitimate. 

“If they don’t need a state permit, then the moratorium wouldn’t be applicable,” he said. “The applicant is saying, ‘We don’t need any official approval from the state because we’re not going to meet any thresholds that would require us to get a state permit. So because of that, the moratorium doesn’t apply to us.'”

State officials haven’t confirmed if NCCS is still subject to this moratorium. 

Massena opens the door
Massena's Town Board meeting on Sep.26. Photo: Richard Haller

Massena’s Town Board meeting on Sep.26. Photo: Richard Haller

Related stories:

Massena’s Town Board recently cleared a path for the data center by voting 3-2 against a local moratorium. Deputy supervisor Samuel Carbone and board members Adrian Taraska and Jared Hollander voted no. Hollander said the project is worth exploring.  

“Data centers, they are being built whether we have a say in it or not, not across the country alone but across the whole globe.  So the opportunity that we have in front of us is control,” he said. 

Supervisor Raymond Lancto and board member Kristy Baker voted in support of the data center restriction. 

Even if this project is exempt from the state moratorium, that does not mean it’s good to go. Hurdles remain, including those from the local government and the state. Massena’s Town Supervisor, Ray Lancto, said developers are just in the beginning phases. 

“There’s a review process,” Lancto said. “It will have to go through the SEQRA process through the state and through DEC, and then it’ll have to gain all those approvals.” 

The DEC would evaluate the environmental, social, and economic impacts that data center construction and operation could have on the area. 

Data center controversy 
Anti-data center protester in Massena. Photo: Richard Haller

Anti-data center protester in Massena. Photo: Richard Haller

This data center has been controversial. Residents across the North Country are concerned it will drive up electricity bills, consume massive amounts of water, and cause noise and air pollution.

NCCS says no local water will be used for cooling the data center because they’re designing a fully sealed loop system.

The St. Regis Mohawk Tribe issued a statement opposing all hyperscale data centers, saying they “pose known and unknown risks that could impact the health and well-being of our community.”

“We met with Town of Massena representatives and sincerely hoped that the Town would not issue authorization for the continued growth of data centers in our area,” the Tribal Council said in a statement.

Related stories:

Akwesasne has a long history of industry giants like Alcoa, General Motors, and Reynolds polluting the land and water around this data center site. Neddie Thompson has lived in Akwesasne her whole life. At a recent anti-data center protest in Massena, she said the town needs to take its time to learn more about this project so history isn’t repeated. 

“I grew up right on that river right next to that GM plant. We didn’t know nothing about what’s going on. We were little. And thyroids started first, then heart trouble, then our organs and our kidneys. We’ve got to get the facts on what this data center is, the noise pollution, the contamination of our water.”

Some people in Massena are supporting this data center because they hope it’ll provide jobs and boost an economy that’s struggled for decades. Mark Ryan was born and raised in Massena and was at a recent town board meeting. 

“When you look at this piece of paper and this information [on the developer’s website], it talks about all the money they’re going to commit to invest in our community. If this is going to be good for our community. How could we turn it down? The community needs a lift,” Ryan said.

The company says the data center will provide 200 full-time jobs and an estimated 2,000 construction jobs. It’s also pledging millions to support local schools, emergency services, roads, and other public services

The Massena Town Board voted 3-2 against a local moratorium. Photo: Richard Haller

The Massena Town Board voted 3-2 against a local moratorium. Photo: Richard Haller

Even if this data center project is exempt from a moratorium, Pfotenhauer from the county Planning Office said he doesn’t expect it to start anytime soon.  

“Projects don’t happen overnight, right? Even if there were some requirements for the moratorium at the state level — this is not going to happen within a year. This project is not going to be built and developed in a year,” Pfotenhauer said.

During that time, he said there could be more regulation that comes out of the state moratorium. 

Massena’s next town board meeting is Wednesday, Oct. 21, 2026, at 4:30 pm. It’s not clear yet if the data center will be included in the day’s discussions.