Phoenix is stationing inspectors at Menlo Digital’s Ahwatukee data center construction site in the early morning and has secured a series of commitments from the contractor to reduce noise and other disturbances following complaints from nearby residents.
The measures include moving construction traffic farther from homes, restricting early-morning deliveries, relocating employee parking and monitoring noise levels around the property.
In an Oct. 9 email to residents, Mike Baxley, assistant director of the city’s Planning and Development Department, said the city met with the construction management team and a representative of the project’s ownership to address neighborhood concerns.
“As with all construction projects, there is a certain amount of noise that the activity of construction will create,” he wrote. “The contractor has committed to taking steps to minimize these aspects of those types of issues.”
Baxley’s email was the city’s latest reaction to months of complaints by residents about construction noise, bright lighting and work they contend was occurring outside legally permitted hours at the million-square-foot Menlo Digital data center campus near 48th Street and Thistle Landing Drive.
“Earlier today we were able to have a meeting with the onsite management team and a representative of ownership for the Thistle Landing project to identify ways to soften the challenges that neighbors are facing with this project,” Baxley wrote.
His email also came days before two developments are set this week, one involving the Menlo project and the other data centers generally.
On Friday, Oct. 16, construction hours return to a wintertime schedule, with crews permitted to work outside only between 7 a.m. and 7 p.m. Monday to Friday unless they secure a special permit from the city Planning and Development Department
City Planning Director Joshua Bednarik several weeks ago told residents in an email his department will not give the Menlo Digital data campus company such a permit.
From 5-6:30 p.m. today, Oct. 14, Attorney General Kris Mayes will hold a town hall on data centers at The Eagles Community Center, 828 E. Broadway Road, Mesa.
“The AG is not investigating the Ahwatukee data center approval,” said Richie Taylor, the attorney general’s communications director. “She is holding a townhall to hear directly from residents about their concerns after receiving multiple complaints from the community.”
Mayes subsequently broadened the the town hall’s scope to data centers generally.
The most significant immediate change outlined by Baxley involves city inspectors.
“Starting today, I have asked our Inspections team to have after hours inspectors onsite, in the morning, each work day to ensure that no activity takes place prior to legal start times through the end of the state mandated early construction” period, he wrote.
“My hope is that this will ensure compliance and allow the neighbors not to have to worry about having to call in a complaint as we will already have an inspector there to handle any infraction of the mandated start times.”
The decision represents a more direct approach to monitoring construction activity than relying solely on complaints from neighbors.
However, Baxley’s email does not indicate that the city has determined any violations occurred.
He said his staff is investigating complaints filed Sept. 12, 24, 25, 26 and Oct. 2 to establish what happened and whether enforcement action was warranted.
“We use a call service that logs the complaints and notifies the on-call inspector that day,” Baxley wrote.
“Once I get more information on the complaints for these dates I can respond further as to what the determination of the complaints were and if any action was necessary.”
The latest development comes as the controversial data center project continues to face opposition from nearby residents, who have raised concerns about its potential effects on their neighborhood.
Much of the broader dispute has centered on the facility’s anticipated operations, including questions about noise, electricity consumption and other environmental and health impacts.
Construction itself quickly evolved as a separate source of friction, particularly for residents living closest to the site.
Craig Evans, president of the Ahwatukee Community Alliance, a nonprofit opponents formed to fight the facility, was not impressed by Baxley’s message.
“It didn’t seem to mean much,” he said. “As far as the City of Phoenix seems concerned, the citizens that do most of the living, working and dying in Ahwatukee…aren’t all that important to the permitting process.
“Disruption to the peace and tranquility of our homes seems an acceptable sacrifice to the City of Phoenix once a permit is issued.”
“Quite frankly Mr. Baxley should be standing in our neighborhood in the small hours making his own recordings and protecting our interests, rather we suspect his are just the latest effort to discount and dismiss the concerns and suffering the City’s decisions have already inflicted on Ahwatukee.”
Evans then lashed out at the city process that got the neighbors in the position they’re now in.
He said the construction permits were not subject to a zoning review Issuance of said permits are not subject to zoning review; but then neither was “the 257MW Hyperscale Industrial Complex going up across the street on a site still zoned for a Commerce Park.”
He reiterated the Alliance’s position that a full rezoning process should have been undertaken in 202, when parent company Menlo Equities of California instead was granted “merely an administrative hearing process intended to review changes to stipulations on existing zoning.
“Such changes might be to signage requirements or possibly returning to prior zoning,” Evans said. “In our research, we found that if more than one stipulation is in consideration for change a zoning hearing is usually required. That was not the case in 2024.”
City officials have said that the zoning change granted the previous site’s owners in 1996 included data centers. The Alliance has argued that data centers at that time were relatively small and usually fit into a larger building.
Evans said, “In 2024, the administrative PHO process was instead used to change multiple existing stipulations on the site, not just to change signage, eliminating the Thistle Landing Office Park monument (because per Menlo’s attorney it is no longer a commerce park); building heights were increased to 56’ or 57’, walkways and driveways that joined with common right of ways were eliminated, walls were added around the site and a small 2-acre park added outside the walls.
“No mention in the new stipulations is made of the expected 5,880 industrial cooling fans that will run 24/7/365 and be located above the 56’ or 57’ building height; nor is there any mention in the new stipulations of the 120 diesel fueled generators capable of producing 257 MW of electricity – enough to energize six Ahwatukee -) and located in equipment yards outside the million-plus square feet of new building space.”
Evans also complained, “Seemingly at every opportunity the City of Phoenix has bent over backward to accommodate construction of this noxious, loud, and exothermic industrial complex on a site zoned for a commerce park, surrounded by homes, preschools, medical offices, churches, and other commercial shops and offices that support and are part of Ahwatukee.
Charging that “Phoenix has avoided established procedures intended to involve Phoenicians like those in Ahwatukee in decisions regarding our investments in the City of Phoenix,” Evans also said city officials were “leaving the responsibility to ‘communicate’ to the same folks who have been walking us up in the small hours of the morning, and disrupting our homes and businesses with excessive dust, noise, and unshielded lighting.”
Baxley’s email outlines several changes the contractor has agreed to make.
Through Oct. 15, when early construction hours are scheduled to end, the contractor has committed not to open the project’s gates or turn on construction lighting before the legally permitted start time.
According to Baxley, “Through the state mandated construction times that end on Oct. 15, the contractor will not open the gates to the project or turn on lighting before the allowed time frame specified by state law.
“Currently that is: Monday thru Friday 5 a.m. -7 p.m. (Concrete pours are allowed to start at 4 a.m.) Saturdays 7 a.m. – 7 p.m. (Concrete pours are allowed to start at 6 a.m.)
Residents have complained for two months that even when concrete pouring is legally permitted before dawn, the equipment and vehicle movements associated with it generated noise.
The site also is flooded with lights that neighbors say have disrupted their sleep.
The contractor also has moved the construction entrance to the opposite side of the project, farther from nearby residences, in an effort to reduce delivery and vehicle noise on the street closest to homes, Baxley wrote.
Sound meters have been installed around the property to monitor noise levels and help determine the direction from which sounds originate, according to Baxley.
The contractor further committed to moving its construction offices and employee parking to an off-site location during the week following the email.
Beginning Oct. 16, Baxley said, the construction schedule will shift to 7 a.m. to 7 p.m. Monday through Friday.
The email does not specify whether city inspectors will continue their early-morning presence after the change takes effect.
Another issue raised in the correspondence concerns how residents are notified when extended construction hours are authorized.
Baxley said a resident reported not receiving notice of extended work hours and explained that the city relies on contractors to distribute the required notifications.
“As part of our permitting of extended work hours we rely on the applicant (the contractor) to make sure that notifications are either sent out or placed on the houses within the required area,” he wrote. “The city does not place them ourselves.”
He said he would ask the contractor how residents were notified and why the resident apparently had not received a notice.
However, Baxley distinguished between work performed under a separate extended-hours authorization and concrete work allowed under state law.
He said notices were not required for concrete placement and related activities conducted during the earlier hours authorized by the state.
The email also revealed a practical obstacle in the city’s review of residents’ complaints.
Baxley said a resident had submitted links to videos showing construction activity, but city computer restrictions prevented him from opening the Google Drive files.
“Unfortunately, I cannot access the videos to gain an understanding of what you are seeing due to our IT department blocking access to google drives,” he wrote.
He asked that the videos be emailed directly so he could review them.
Baxley said he had recently assumed oversight of the city’s inspections division and was working to familiarize himself with the project’s history and the complaints raised over the summer.
He also included representatives of the construction management team and Menlo Equities in his correspondence so they could provide additional information about efforts to reduce the project’s impact.
The email does not establish whether the contractor has completed all the promised changes or whether residents have noticed any improvement.
Nor does it resolve whether the five dates identified in the complaints involved violations of construction-hour restrictions.
For now, the city’s response provides a series of specific measures against which future construction activity can be evaluated.
“I have added the construction management team for the project and the onsite representative of Menlo Equities to this email so they can add anything that I might have missed from our discussion of how they are trying to mitigate issues from the construction of the project to surrounding neighbors,” his email added.