The owners of the Albany Center for Independent Living are working to reopen the facility after the town of Bethlehem ordered the facility to close over failed building inspections.

The owners of the Albany Center for Independent Living are working to reopen the facility after the town of Bethlehem ordered the facility to close over failed building inspections.

Will Waldron/Times Union

BETHLEHEM — The owners of a Delmar assisted living facility forced to close its doors last month over failed building code inspections say they are working “diligently” with town officials to reopen the facility and eventually welcome back residents.

The 67-bed Albany Center for Independent Living on Rockefeller Road was slapped with a “notice of imminent danger” and an emergency order to vacate the property by the town of Bethlehem’s Building Division on Sept. 3. The order was handed down after a rash of serious safety violations were documented during two days of inspections in late August.

Article continues below this ad

All 45 residents were relocated to new homes with assistance from the state Department of Health, some far away from relatives, while staff had to be moved to other facilities or were forced to claim unemployment.

Previously: Bethlehem calls Albany Center for Independent Living ‘unsafe for occupation,’ orders facility to close

“We know this displacement has been difficult for residents, families and staff, and we are committed to working with the town and the New York State Department of Health to reopen the facility as swiftly as possible,” Tara Hogan, regional director for the nursing home’s operators, said in a statement.

Photos and videos collected by building inspectors to document code violations show rodents and bugs, exposed electrical wires, chipped paint and water-damaged ceilings and walls at the Albany Center for Independent Living in Delmar. Bethlehem town Supervisor David VanLuven has described conditions inside the building as “unsafe for occupation” as its owners push to reopen the facility. (Video courtesy Town of Bethlehem)

Times Union

But while a town attorney and the nursing home’s owners, citing an independent report, say that the building is structurally sound, the town’s own records suggest its residents faced deteriorating living conditions.

Article continues below this ad

The Times Union reviewed more than 100 pages of fire and building inspection reports, letters sent to the owners by town building inspectors, as well as video and photo documentation that were obtained through a Freedom of Information Law request. The records reveal widespread water damage and active leaks, rodent and bug infestation, peeling paint, mold and unidentified filth inside the facility.

This still, taken from a video filmed during a building inspection, shows a rodent at the Albany Center for Independent Living in Delmar.This still, taken from a video filmed during a building inspection, shows what appear to be roaches in a piece of furniture at the Albany Center for Independent Living in Delmar.

These stills, taken from videos filmed during a building inspection, show what appear to be a rodent and bug infestation at the Albany Center for Independent Living in Delmar.

Photos courtesy of town of Bethlehem

These stills, taken from videos filmed during a building inspection, show what appear to be a rodent and bug infestation at the Albany Center for Independent Living in Delmar.

Photos courtesy of town of Bethlehem

Code violations included an active combustible gas leak in the kitchen, electrical hazards including unapproved lighting installations and exposed wires, and condensation in the HVAC system due to an ongoing roof leak, according to inspection reports. 

Article continues below this ad

Also due to the roof leak, inspectors observed “multiple locations with water damaged and soaked ceilings” and “walls and floors with observed black substances adhered to such surfaces indicating potential black mold growth,” according to the notice.

The notice highlighted an “unsafe and inoperable elevator system” in the building as well. Emergency personnel have responded to multiple calls to the building to rescue trapped occupants, according to the notice.

Water damage on ceiling tiles at the Albany Center for Independent Living in Delmar was found by the town of Bethlehem's building inspectors.Inspectors observed “multiple locations with water damaged and soaked ceilings” and “walls and floors with observed black substances adhered to such surfaces indicating potential black mold growth,” according to a notice from the town.

Images collected by the town of Bethlehem’s building inspectors from inside the Albany Center for Independent Living in Delmar show what the town supervisor has described as conditions “unsafe for occupation.”

Courtesy of town of Bethlehem

Images collected by the town of Bethlehem’s building inspectors from inside the Albany Center for Independent Living in Delmar show what the town supervisor has described as conditions “unsafe for occupation.”

Courtesy of town of Bethlehem

According to records from the state Department of Health, the facility was inspected 30 times between April 2022 and March 2026, resulting in 77 violations. Many of those inspections predate the current owners.

Article continues below this ad

The facility was purchased last year by New Jersey-based Emerald Health Care Group as part of a $7.5 million deal that also included the 120-bed Delmar Center for Rehabilitation and Nursing down the road.

Earlier this week, representatives from Emerald Health Care Group reached out to the Times Union to speak about the steps it has taken, including getting an independent engineering firm, REL Engineering PC of New Jersey, to evaluate the integrity of the building. 

“The independent engineering report found stable, intact structural systems and no imminent structural danger. It documents corrective measures already taken and a plan for remaining repairs and certifications,” Hogan said.

The company declined to comment when asked to respond to the conditions shown in inspection reports.

Article continues below this ad

Town attorney Mark Sweeney said that many of the outstanding issues still need to be corrected, especially involving water damage, water leaks and mold.

Sweeney said that while that engineering report may have found there is “no imminent structural” danger, more inspections have to occur of the water damage and mold issues inside the walls, requiring sheetrock removal.

“It wasn’t just the structural issues,” Sweeney said. He said there is no timeline yet for a reopening.

Records obtained by the Times Union show that the town initially tried to get the company to fix the problems within 20 days without forcing residents to leave. That was after a Sept. 1 inspection. But Sweeney said that on Sept. 2, the following day, more serious water leaks were found, prompting the codes department to issue the emergency order to vacate.

Article continues below this ad

“We found more issues of concern that needed to be addressed immediately,” Sweeney said.

Sweeney said the owners are in the process of replacing the roof and have applied for a building permit for that work. The elevator is still being worked on, and natural gas service must ultimately be restored. The owner has been clearing the stairwells, he said.

“Other inspections and work to evaluate the windows and doors to identify and remediate any leaks is underway by the owner’s contractors,” Sweeney said. “We’ve been working very closely with the owner. They’re responding to our requests.”

John Emery, a spokesman for the state Department of Health, said the department has been in “regular communication” with the displaced residents and their families and the “receiving facilities” where they are currently living. 

Article continues below this ad

The town ultimately makes the decision on when the building is safe again, he said, adding that the DOH “takes the health and safety of adult care facility residents very seriously.”

Employees were also displaced by the facility’s closure.

Coleen Hemmings, vice president of 1199SEIU United Healthcare Workers East, which represents the facility’s former workers, said the union wants employees to return to work, but also wants the facility to improve conditions, both for residents and for employees.

“They do want to go back, but they want to go back to a facility where it’s safe to work,” she told the Times Union. “Because working in the mold and the electrical issues and the elevator being broken down — they want to make sure that it’s back up and running in a safe and proper environment for them to go back so they’ll be able to take care of those residents.”

Article continues below this ad

According to Hemmings, three employees — two dietary workers and one recreation aide — from the Albany Center for Independent Living were placed at the company’s other local facility, the Delmar Center for Rehabilitation and Nursing. The union was able to negotiate for the rest of the employees to be paid for the first two weeks following the closure. After that, Hemmings said, employees used their remaining PTO and then began collecting unemployment.

“We really need to get these members back to work, and the residents have been calling to see when they can go back to their home,” she said.