The overpromised, over-budget Automated People Mover project has become a flashpoint in the tight race for Los Angeles mayor as a video clip appears to show electrical explosions along its tracks.

The automated electric train system, now called LAX SkyLink, aims to connect LAX terminals with Metro and move passengers around the airport without having to rely on cars or shuttle buses. It was originally scheduled to be ready in 2023 before its opening was pushed back repeatedly, most recently to February 2027.

A day after a poll showed Mayor Karen Bass and LA Councilmember Nithya Raman in a dead heat, the mayoral challenger attempted to link the project’s delayed completion to the incumbent mayor.

The project has gone about $1.4 billion over budget, according to an LA Times report.

“The opening keeps getting moved back, the opening keeps getting moved back, and Angelenos have every right to doubt the next date they are given,” Raman said, seizing on the LA Times report, which attributed part of the delay to a dispute involving the Los Angeles Department of Water and Power (LADWP) and Los Angeles World Airports (LAWA) over the use of solar power to operate the train.

“If her own departments can’t resolve a disagreement holding up a multi-billion dollar project … Where is the Mayor? She is once again missing in action,” Raman said.

But Bass pointed out that the train project was approved and launched before she took office, during the Eric Garcetti administration. Noting that there have been disagreements among several private contractors on the project, Bass said delays have also been the result of safety concerns.

“We obviously don’t want people on the people mover until we are guaranteed that it is safe,” Bass said. “I anticipate that that should be by the first of the year because if it’s not, then one of the contractors is going to face severe financial penalties.”

The mayor appoints the heads of both LAWA and LADWP.

Newly surfaced video, shot in late September, also appears to show an electrical blast along the train tracks. According to an October report from LINXS, the contractor building SkyLink, there were three arc flashes on the tracks on Sept. 23 and Sept. 25.

A LAWA fact sheet said, “Arc flashes are not uncommon for these projects, particularly in the testing phase. Finding and fixing issues like these is exactly what testing is for.” LAWA added that the problem areas had been repaired.

The train must complete 30 consecutive days of successful testing before it can move forward in the safety certification process.

Marshal McClain, an LAX police sergeant and president of the police union that represents LAX officers, expressed doubts about the progress of the train project.

“We don’t feel like the management of the airport is taking enough account of the safety of the operation of the SkyLink,” McClain said.

The contractor’s report also cites delays related to safety, as well as disputes with LAX and the LADWP over solar power. The contractor has also sued the city of Los Angeles.