Check out five upcoming and ongoing transportation projects around Dallas-Fort Worth.

This list is not comprehensive.

Upcoming projects

  1. Park Boulevard arterial concrete repair

Project: The city of Plano is removing and reconstructing a concrete arterial street and sidewalk along Park Boulevard from US 75 to the east city limits.

Update: Bids for the project opened in mid-October and construction is estimated to start in late November or early December, city officials said.

  1. East Bethany Drive Asphalt Overlay Project

Project: The scope of the project includes constructing a protective layer of asphalt over the existing pavement to extend the life of the roadway, city of Allen documents state.

Update: The construction contract has been awarded to Overland Corporation, city officials said. 

  • Timeline: Construction expected to begin no later than April 15, 2027

  • Cost: $1.6 million

  • Funding source: city of Allen

Ongoing projects

  1. Richland Park Drive reconstruction 

Project: This reconstruction project in Richardson includes two segments: Sheffield Drive to Tiffany Trail and Stillmeadow Drive to Wentworth Drive. Crews are rebuilding the roadway along the two segments while replacing utility lines under the road.

Update: Work crews continue to install utilities along the street. Paving for the northbound travel lanes is also ongoing.

  1. Mahard Parkway construction

Project: Mahard Parkway in Frisco is being constructed from PGA Parkway to US 380 and will have six lanes. The project borders the Firefly Park development.

Update: The project is under construction and expected to wrap later this year.

  1. Keller Hicks Road improvements Phase 2

Project: The second phase of Fort Worth’s Keller Hicks Road project includes the installation of a three-lane section from Park Vista Boulevard to Lauren Way, new street lights, sidewalks, drainage and a traffic signal at Woodland Springs Drive.

Update: The first phase of the project, which spanned from Lauren Way to US 377, was completed in spring 2025. For the second phase, traffic is one-way traveling west on Keller Hicks Road, but two-way traffic will likely return if the final concrete lane and driveways are completed by December 2026 as expected.