Plano ISD is renovating an elementary school and a multifamily project is planned for north Fort Worth. Check out some of the latest construction filings with the Texas Department of Licensing and Regulation.

  1. Andrews Elementary School renovations in Plano

Plano ISD‘s Andrews Elementary School will receive new flooring, a restroom renovation and fire alarm replacement per a TDLR filing. The renovations are part of a number of districtwide projects approved by voters during the district’s 2022 bond program, according to the district. Over a quarter of 2022 bond projects were completed as of October 2025, per previous reporting.

  • Location: 2520 Scenic Drive, Plano

  • Estimated timeline: May 21, 2027-Aug. 10, 2027

  • Estimated cost: $2 million

  1. Multifamily project in north Fort Worth

Ten four-story garden-style multifamily buildings will be constructed in north Fort Worth near Alliance Town Center, per a TDLR filing. Some amenities at the development, known as Range Citadel, include a clubhouse building, three detached garage buildings and surface parking.

  • Location: 9565 Citadel Way, Fort Worth

  • Estimated timeline: March 31, 2027-April 1, 2029

  • Estimated cost: $40 million

  1. Associa expansion in Richardson

The real estate company, Associa Development Group, Inc., is expanding its headquarters in Richardson. A 23,000-square-foot, two-story corporate office will be constructed at an existing campus, per a TDLR filing. The new facility will have conference, meeting, event and support spaces. Associa first announced its relocation from Dallas to Richardson in 2024, per previous reporting.

  • Location: 1300 Lookout Drive, Richardson

  • Estimated timeline: Dec. 1, 2026-Dec. 1, 2027

  • Estimated cost: $8 million

  1. Ford Middle School renovations in Allen

Allen ISD’s Ford Middle School will receive a new track and field with bleachers and a press box, per a TDLR filing. The renovations are funded by a voter-approved 2024 bond, according to the district website.

  • Location: 630 Park Place Drive, Allen

  • Estimated timeline: Dec. 15, 2026-Aug. 1, 2027

  • Estimated cost: $7 million

  1. New retail in McKinney

A one-story retail facility is planned to be constructed at the intersection of US 380 and Terry Lane in McKinney, per a TDLR filing. The development is located on 5 acres and the full project is expected to have two buildings, according to the developer website.

  • Location: US 380 and Terry Lane, McKinney

  • Estimated timeline: Dec. 15, 2026-June 15, 2027

  • Estimated cost: $5.2 million