After spending three months developing recommendations on how Fort Worth can best regulate data centers, the Data Center & Infrastructure Commission unveiled its findings to city leaders Tuesday.
The 11-member commission developed 19 recommendations across water and natural resources, land use, economic impact and electricity — all of which are detailed in a 156-page report.
The committee’s findings, some of which build on existing ordinances, were presented to city council members by Michael Slattery, environmental director at Texas Christian University and director of its Institute for Environmental Studies, who was tapped by the city to lead the advisory group. In a meeting following the presentation, council members also held the city’s first public hearing on Fort Worth’s adoption of the 90-day moratorium, as required by state law.
The committee was formed after zoning commissioners in July voted down proposed regulations on zoning requirements for data centers, recommending Fort Worth staffers create stricter ordinances. That vote prompted city officials to make three votes related to data centers on Aug. 11, including the inception of the advisory group and the moratorium process.
Slattery prefaced his presentation to council members by saying data center development is the most contested land-use issue in Fort Worth, adding the commission’s goal was to produce an evaluation of data center development based on fact, not advocacy.
“Skepticism is healthy and it’s exactly why getting the science right in this commission absolutely mattered,” Slattery said.
The report was developed by the advisory group’s 11 members. The formation of the group was approved by the city in early August and consists of representatives with backgrounds in economic development, data centers and related infrastructure, natural resource management and environmental advocacy.
The commission and its findings are intended to guide city staffers on how best to regulate data center development amid a nationwide boom in the tech hubs and opposition from communities.
The recommendations include a potential regulation for the city to require a “zero-water” solution, echoing what Fort Worth officials proposed earlier this year. Under this regulation, data centers would need to equip a nonevaporative, closed-loop technology supplemented with limited adiabatic cooling — the process of cooling ambient air through controlled evaporation.
Commissioners also recommended making water usage publicly available, as well as protecting local water supplies through utility and service reviews.
On proposed electricity regulation, the group’s members recommend Fort Worth require a technical fact sheet from developers and include verifiable commitments that would relieve strain on the electric grid.
The recommendation related to land use that Slattery spoke to most was the committee’s proposal to protect homes with zoning standards that can be measured. That involves requiring a minimum 350-foot setback between homes and a data center and establishing a framework to enforce noise limits.
Setbacks between properties should increase if data centers and their infrastructure’s height increase, Slattery said.
Council member Jeanette Martinez said she would like to see larger setbacks between homes and data centers.
“I foresee that people will probably make that request,” on increased separations between properties, Martinez said.
Asked by council member Chris Nettles how the decision on the proposed setback was made, Slattery explained that the committee analyzed distances between properties in other cities, adding that most residents would like to see data centers located as far away as possible.
“We have to find something that is realistic, that is enforceable. I absolutely hear what you say,” Slattery said.
In a briefing with reporters following the presentation, Slattery said the biggest disagreements among the commission’s members came on the decision to recommend a 350-foot setback.
It was critical for recommendations from the group’s members to be science- and research-backed, Slattery added.
The land-use proposals also call on the city to include thermal impacts and community feedback on data centers in Fort Worth’s 2050 comprehensive plan, the document that details the city’s vision and long-term planning.
The recommendations covering the report’s four sectors were developed to tailor what city officials have authority over. The document details that major power decisions are made by power distributors and state officials.
Council member Elizabeth Beck asked why land-use recommendations did not detail zones in which data centers can be developed.
The committee decided to not make recommendations on how data centers should be zoned so the city could put in place regulations that would be protective of residents without restricting the data center industry, Slattery said.
“I don’t want that to sound like advocacy. … The data center developers that I spoke with wanted certainty and they wanted predictability. And they said, ‘Whatever you folks come up with, we will work with,’” Slattery said.
The commission’s report comes as lawmakers prepare to deliberate various facets of data center operations and development in the upcoming 90th legislative session.
Fort Worth officials went back-and-forth on creating and implementing data center regulations earlier this year, stating local control could be affected by directives from Gov. Greg Abbott — while he serves the remainder of his term — and laws that come out of the Texas Capitol in 2027.
During her campaign run, Gov.-elect Gina Hinojosa said she would continue a statewide data center moratorium until legislators meet in January, adding she would pass “real protections” for communities, The Texas Tribune reported.
A day after bill filing opened, the Legislature’s agenda was filled with hundreds of bills, including proposals on regulating data centers.
State Rep. Salman Bhojani, D-Euless, who was just reelected to represent House District 92, filed a bill to amend Texas’ water code. It would require data centers to disclose the entity supplying their water and how much resources a development would consume.
Republican Armin Mizani, House District 98 representative-elect and former Keller mayor, filed a bill to give local government officials the authority by a voting process to determine whether a data center can be built in a city or county in which they govern.
Also in their evening meeting, council members held the first hearing on Fort Worth’s adoption of a 90-day moratorium on all new data center projects, as required by state law.
Nicole Lopez is the environment reporter for the Fort Worth Report. Contact her at nicole.lopez@fortworthreport.org.
The Report’s environment coverage is supported by the Marilyn Brachman Hoffman Foundation.