It’s been a decade-long slog for developer Sunroad Enterprises and the Port of San Diego to deliver a new 450-room hotel on Harbor Island. And it’s now about to get longer — yet again.

For the second time in as many years, Sunroad is asking the port to give it more time to fulfill an obligation to break ground on the long-delayed $200 million project.

Tuesday, the Board of Port Commissioners for the San Diego Unified Port District will consider an amendment to Sunroad’s option to lease agreement. The proposed amendment seeks to extend the contract’s term by two years, through Dec. 31, 2028. It also requires the developer to reimburse the district up to $100,000 if the Port opts to build a pedestrian path on the project site.

Agency staff are recommending approval.

“The hospitality market has faced considerable headwinds, with substantial increases in hotel construction costs and interest rates for hotel financing,” a staff report prepared for the board meeting states. “Due to these changes in market conditions, Sunroad has requested additional time to secure financing for the project and satisfy the other option conditions necessary to enter into the lease and commence construction of the project.”

In July 2021, Sunroad first entered into the option agreement with the Port to redevelop a 7.5-acre parcel at 851 Harbor Island Drive. The agreement, which has been amended twice in the ensuing years, calls for the parties to execute a 66-year ground lease at the end of the option period.

Under the most recent agreement, the San Diego developer was required to start construction by the end of this year. But Sunroad says that’s no longer possible, and port officials acknowledge the need to extend the previously imposed deadline by two years, given what is still a challenging environment for financing new hotel development.

As recently as August, Sunroad CEO Uri Feldman told the Union-Tribune he was still hopeful about being able to start construction by year’s end.

The development plan contemplates what is essentially two hotels in one — a 198-room extended-stay hotel and a 252-room limited-service property that the port has referred to as a “micro hotel” varying in height from 12 to 15 stories.

The hotel also would include several amenities, including a walk-up restaurant and bar area, swimming pool, Jacuzzi spa, fitness center, retail space, conference space, and a 15-foot-wide waterside public promenade.

Sunroad has yet to reveal a chosen hotel brand for the East Harbor Island resort. The Port has previously asked that the operator be upscale, akin to a Marriott, Hyatt, Hilton or Swissotel.

At the time that Sunroad sought its last extension — in 2024 — Port staff said the extra time was needed so that Sunroad could finalize its financing and determine how to satisfy a requirement to address the need for affordable overnight accommodations.

Toward that end, Port commissioners last year granted Sunroad some $19 million in rent concessions. The favorable new lease terms were necessary, Port officials said, because of a still challenging commercial real estate market that made financing more difficult to obtain.

Among the approved concessions were new lease terms that will not only postpone the start of rent payments but also lower them for the first seven to 10 years of the lease term. The Port also agreed to evenly split the cost of an “in-lieu” fee of up to $11 million that is required to satisfy the California Coastal Commission’s longstanding demand for affordable lodging on state tidelands, which in San Diego County are overseen by the Port.

Manchester Financial Group executive Ted Eldredge says it’s not surprising that Sunroad would need yet another time extension. His company is experiencing similar difficulties in landing financing for development of a 36-story Fairmont hotel overlooking San Diego Bay. Although plans for the high-rise were announced in 2022, construction has yet to take place.

“The equity and debt markets are still very difficult, and interest rates are going up,” said Eldredge, president of Manchester Financial. “Investors have been buying existing hotels instead of putting their money into ground-up construction. I think it’s improving, but it will take some time. Eventually, all those deals to buy existing hotels will be non-existent, and the only place for investors to put their money will be in ground-up construction.

“We’re in line as well.”

While the extension request is coming to Port commissioners a little more than a month before the approaching deadline for a groundbreaking, hints that more time might be needed started to emerge earlier this year. A public records request from the Union-Tribune seeking email communications between Port staff and Sunroad revealed, for instance, that twice the developer needed more time to complete its working drawings for the hotel.

In another communication, a Port staffer advised Feldman in July that there were a number of “time-sensitive” issues that needed to be addressed during an upcoming meeting, including the project design, status of a hotel management agreement, an update on project financing, and whether an “extension to termination date” of the lease agreement will be requested.

While Sunroad’s current hotel project dates to 2016, the developer’s quest to bring a hotel to Harbor Island started many years earlier when it began working on a more modest 175-room hotel. That project, though, failed to advance after repeated denials from the California Coastal Commission, which was less troubled by the hotel project itself than by what it saw as the Port’s resistance to reserving more of its state tidelands for lower-cost lodging.