By Tiffany Toru Johnson, Fort Worth Report
November 14, 2026

Officials presented plans for the second phase of improvements to the intersection of Marine Creek Parkway and Northwest Loop 820. 

This federally funded project aims to reduce traffic congestion and improve safety by adding turn lanes, updating traffic signals, rebuilding medians, and reconstructing sidewalks and curb ramps to meet ADA standards.

The first stage of construction saw the installation of an eastbound U-turn lane and the addition of 10 trails on the east side of Marine Creek to connect to a future park, according to the city website.

Construction is scheduled to begin on Nov. 30 with completion anticipated in August 2027. Work will be completed in phases, starting on the Loop 820 frontage roads, followed by Marine Creek Parkway and pedestrian improvements.

During the meeting, Fort Worth City Council member Carlos Flores and city staff said additional outreach efforts, including website updates, social media announcements, message boards and neighborhood notifications, will be used to keep residents informed throughout construction.

There are also plans to provide more direct notifications to an apartment complex and nearby businesses. Another virtual meeting will also be available sometime next week.

City representatives said the improvements are designed to improve traffic flow while creating a safer and more accessible intersection for drivers and pedestrians alike.

Marine Creek Parkway Intersection Meeting

Documenter: Tiffany Toru Johnson

Date: Nov. 9, 2026

Learn more about this project by clicking here. To watch a video of the meeting, click here.

Tiffany Toru Johnson is a member of the Fort Worth Report Documenters crew. If you believe anything in this account is inaccurate, please email us at news@fortworthreport.org with “Correction Request” in the subject line.

This article first appeared on Fort Worth Report and is republished here under a Creative Commons Attribution-NoDerivatives 4.0 International License. ""