The data center’s 5,500 estimated employees at peak construction will strain area roads without some sort of mitigation to add capacity for construction work, she said. Construction will require civil crews, concrete workers, ironworkers, electricians and heavy equipment operators, Mayes wrote. 

Building nine 493,000-square-foot buildings for the center, installing roughly 6,150 Megapack battery containers, and upgrading nearby substations will generate sustained semi-truck and oversized-load traffic for concrete, steel, transformers, and cooling units, she said. 

A Megapack is a utility-scale battery that provides reliable energy storage to stabilize the grid and prevent outages, according to the website of Tesla, Musk’s electric car manufacturing company.

The construction work will very likely increase wear on rural two-lane stretches of U.S. 191 and surrounding county roads, Mayes wrote.

“To protect the safety of its citizens and the integrity of its existing transportation networks, the county should commission a third-party study of the traffic impacts and develop a plan to ensure upgrades will be in place before construction begins,” Mayes wrote.

SpaceX, however, said its data center application already calls for a traffic impact analysis that would be reviewed by the Arizona Department of Transportation and construction of turn, acceleration and deceleration road lanes when required by the state agency. In addition, SpaceX said it will fund an independent review of the traffic impact analysis.

Interference with military activity 

The Willcox Playa, which borders the data center site, is also used by Fort Huachuca and the U.S. Army Electronic Proving Ground for live fire and outdoor electronic testing, Mayes wrote. The military uses the playa’s interference-free environment to test GPS jamming, radar systems, unmanned aerial systems and communications equipment, she wrote.