As a planned 1-million-square-foot data center-office campus continues to roil Ahwatukee, a new state report cited such facilities and other “large-load” customers as a challenge to grid reliability and electric rates.

 In a lengthy report released last week, the Governor’s Office of Resiliency’s Arizona Energy Promise Taskforce called for “a suite of policy considerations to enable Arizona to accommodate economic growth without compromising grid reliability or unfairly increasing costs for existing customers.”

“The volume and pace of large-load customer growth require new, customized approaches to accommodate economic development while protecting residential and other ratepayers,” it says.

It adds that the pace of large-load facility construction is exceeding historical growth patterns and challenging how utilities make investment and planning decisions.

It also warns, “The operating profiles of large-load customers, particularly data centers that operate continuously, pose unique challenges for grid operations and maintenance. 

“Arizona utilities traditionally schedule maintenance during periods of lower demand, such as winter months with reduced air conditioning use. Continuous demand from large load facilities can limit these windows, requiring changes to maintenance practices, redundancy planning, and outage management to preserve reliability. 

“Large-load growth is occurring across utility service territories and impacting regional infrastructure systems, creating a need for greater coordination.”

Scores of business leaders and professionals were on the panel that produced the report.

Gov. Katie Hobbs called on them to outline how the state can “streamline and expedite plans to build energy infrastructure and expand Arizona’s energy system, while maintaining the state’s legacy of responsible natural resource management, reliability, and affordability.”

The report alludes to data center development in Chandler and Phoenix.

However, it does not include any mention of California-based Menlo Equities’ five-building, 1-million-square-foot project on 40.6 acres on the southeast corner of 48th Street and Thistle Landing Drive.

Menlo already has cleared the parcel of a four-building call center that had been on the site, which it bought in 2015 for $52 million.

Neighbors have mounted a fight to block the project, for which zoning was changed in 1997. 

Though the developer appeared before the Ahwatukee Foothills Village Planning Committee on Jan. 22, 2024, Menlo’s appearance was clearly identified by a city planner as a “courtesy presentation” because the zoning already had been in place for nearly 30 years.

The committee did recommend some changes to site plan stipulations that were made when the rezoning was approved in 1997 and the city Planning & Development Department subsequently approved them as well.

Nevertheless, nearby homeowners are continuing to press their fight to stop the project, expressing concerns about the center’s impact on health, electric and water rates and their overall quality of life as a result of noise from the facility.

Opponents have gathered over 1,000 signatures in an online petition at change.org.

The taskforce report notes, “Community concerns related to water use, energy affordability, visual impacts, noise, and other effects can delay or halt projects. Large-load facilities can have significant implications for water use and air quality, which is particularly concerning in Arizona.”

It says “there is no comprehensive reporting of the water usage associated with electricity generation” and that “information about the water footprint of various energy sources within the state is limited.”

While it may not mention the Menlo Equities project, the report echoes the concerns that have arisen about it.

The report focuses on the long-term health of the state’s electrical grid as more data centers and other large electricity consumers come online.

It notes, “Supply chain limitations for critical equipment, including transformers, switchgear, and transmission components, are driving up costs and further extending construction timelines.”

And it cites a disconnect between data center operators’ time frames for connecting to power supplies and utility companies’ ability to meet them.

“Long lead times for new generation, transmission, and distribution infrastructure limit how quickly capacity can be added and may not align with interconnection timeframes requested by large-load developers,” the report states.

The task force repeatedly points to “large load” customers – a category dominated by data centers – as a defining challenge.

“These facilities can require substantial and concentrated energy demand,” the report notes, warning that such growth creates “challenges for reliability [and] affordability.”

Unlike traditional growth, which tends to be gradual and distributed, data centers can bring massive, immediate spikes in demand, requiring utilities to build infrastructure years in advance.

The state report echoes a recent story in Politico on the pressure data center growth is putting on the nation’s electricity grid. 

“The entire system is trying to grow faster on the supply and the demand side, and we have a limited number of transformers we can crank out,” Josh Rhodes, a research scientist focused on energy with the University of Texas, Austin, told Politico. 

Rhodes also said everyday ratepayers will end up paying more on their power bills, Rhodes said.

“I expect electricity prices to go up,” he was quoted as saying. “If you look at the inflation on the infrastructure that moves electricity around, it has vastly outpaced [the Consumer Price Index] in terms of inflation on things like eggs.” 

The news site also said some data centers can generate $10 million in revenue in a single day, making the rising cost of transformers and other electrical equipment “negligible” in the data center owners’ eyes, one electricity provider executive told the news site. 

Across the Valley, utilities are increasingly planning clusters of projects rather than single facilities – a shift driven by the scale of demand. As a result, the report states, energy demand is arriving in large, concentrated bursts.

One of the report’s most pointed concerns involves who bears the burden of building out the infrastructure needed to support that growth.

The task force calls for “greater transparency” and “fairness in cost allocation” for large users, warning that without changes, rapid expansion could place “upward pressure on rates.”

“Changes in ratepayers’ utility bills are driven by a variety of factors, including system load growth, fuel prices, and natural hazard damages,” the report states. “While data from some states have shown that load growth can decrease retail prices … there is still uncertainty regarding the conditions that must be met to achieve such reductions.

“Importantly, cost reductions related to load growth are not guaranteed, as seen in other states.”

It also notes, “In Arizona, the largest cost driver for Arizona ratepayers is the need for cooling during heat season. A ratepayer’s total bill is thus particularly sensitive to their consumption rate.”

That raises a central question already emerging in policy discussions: Should residential customers subsidize infrastructure needed for billion-dollar data centers?

Utilities have already signaled that major investments in generation and transmission will be required — costs that could eventually flow through to ratepayers if not structured carefully.

And while “the volume and pace of large load customer growth require new, customized approaches to accommodate economic development while protecting residential and other ratepayers,” the report notes a fragmented decision-making landscape for making those decisions.

“Ultimately, the adoption of any framework and the implementation of any practices are solely within the jurisdiction of the relevant ratemaking body,” it states.

“Depending on the relevant utility or power provider, the decision-maker may be the Arizona Corporation Commission, the Salt River Irrigation Project’s Board of Directors, Co-operative Board of Directors, Tribal Utility Authorities, or others.”

The report notes that both Phoenix and Maricopa County, as well as other cities and counties in the state, have instituted new zoning requirements for data centers, though they do not apply to projects that have long been approved, including Menlo Equities’ campus.

It also calls on state policy makers to not only look at further development of new sources of energy, such as solar power.

It also urges them to examine how other states are planning to shield residential customers from a major impact on their bills.

“Many public utility commissions and utilities have initiated or implemented specialized large load tariffs to protect ratepayers and mitigate stranded asset risks,” the report states, saying over 100 of such controls already have been adopted across the country.

Those measures provide “enhanced contractual protections beyond standard utility service terms to prevent costs from falling on residential and small business customers”; “reduce speculative development and associated stranded asset risks”; and “align infrastructure investments with demonstrated demand.”

The report acknowledges that data centers, along with semiconductor manufacturing and other advanced industries, are viewed as key to positioning Arizona as a national technology hub.

“With the adoption of a statewide framework that prioritizes transparency, oversight, and community empowerment,” it says, “the state can attract responsible economic development in communities that desire it, while shielding residential and other ratepayers from cost shifts, unmitigated risk, and natural resource depletion.”