Check out three road project updates in League City.

Completed project

League City Parkway right-turn lane

Project: An eastbound right-turn lane was designed west of Butler Road to west of the I-45 southbound frontage road, and tied to the Texas Department of Transportation’s right-turn lane, according to city officials.

Update: The project is complete and the roadway is now open to traffic.

  • Timeline: completed in March
  • Cost: $2.08 million
  • Funding source: Galveston County bond funds

Ongoing project

FM 518 at Country Lane intersection improvements

Project: This is a full intersection rebuild at FM 518 and Country Lane, including signal upgrades, mast arm installation and safety enhancements, according to city officials.

Update: Construction started in late April due to a wait on signal equipment.

  • Timeline: slated to wrap in the fall
  • Cost: $504,000
  • Funding sources: city reinvestment funds

Upcoming project

Traffic signal at Lawrence Road and Village Way

Project: The project scope includes a design and rebuild of the traffic signal at the intersection, according to city officials.

Update: Construction is slated to begin in May.

  • Timeline: estimated to take a year to complete, varies depending on delivery of new signal apparatus
  • Cost: $573,000
  • Funding sources: city reinvestment funds

“>