A section of the former Pfizer headquarters building sits under construction on Wednesday.

The developer of the Midtown Manhattan high-rise that was evacuated Tuesday after structural columns buckled is insisting “at no time was the building, or any portion of it, at risk of collapse.”

“Reports of risk of a collapse were and are inaccurate,” a statement from Metro Loft said Wednesday.

The statement contrasts with public assessments from the FDNY and city officials on Tuesday, who described the building as “unstable,” established a formal “collapse zone” around it, and said they had monitored continued movement of the structure.

The company said its team worked through the night stabilizing the affected columns, rendering the structure stable.

“We have identified the issue and developed a clear plan to fix it,” Metro Loft said. “We are in the process of addressing the issue and will fully rebuild this portion of the building in tandem with ongoing construction.”

The construction project remains on schedule, according to the developer, who added that work to rebuild the buckled sections would not delay delivery of the building itself. “This is a localized situation affecting less than 30 apartments out of over 1,600,” the company said.