Though details are not being provided, the city of Scottsdale and Scottsdale Unified School District are becoming close partners.
Rather than honors or photo opportunities, this is a strictly business relationship – as the city and school district are wheeling and dealing on two prime properties.
Following a potential rental deal, the newest is a property sale.
On March 30, SUSD quietly called a “special meeting” held via online participants.
After a brief introduction, board members Matt Pittinsky, Donna Lewis and Mike Sharkey voted to go into executive session; board members Amy Carney and Carine Werner were not present.
According to the agenda, the private meeting was “for the purpose of obtaining legal advice and instructing its representative regarding the potential sale of 7575 E. Main Street, Scottsdale.”
Attorneys Jennifer MacLellan and Laura Server Blanco, both of the firm Gust Rosenfeld, were also present. The latter “concentrates her practice on real estate transactional law,’ according to the firm’s website.
After a brief conference, the board returned to public and voted 3-0 “to direct the attorney for the public body to negotiate the purchase agreement with the city of Scottsdale with the changes to the proposed letter of intent as discussed in executive session.”
SUSD Superintendent Scott Menzel later clarified: “The potential sale of the Main Street property has been under consideration going back to last fall.”
Scottsdale City Manager Greg Caton did not respond to a request for comment on the city’s potential purchase.
City-SUSD lease
The April 14 Scottsdale City Council advanced agenda includes:
“Authorize Contract No. 2026-044-COS with Scottsdale Unified School District for the temporary use of office space located at the Oak Learning Center, 7501 E. Oak Street for the relocation of city staff to accommodate city construction project at the jail and police facility.”
According to the city’s webpage tracking 2019 voter-approved bond projects, the $13 million “Renovate and Expand the Civic Center Jail and Downtown Police Facility to Meet Demand” project is in the design phase.
Asked about the proposed SUSD lease, Holly Peralta, a city spokeswoman, responded, “We are making some improvements to the Kiva to enhance acoustics and update technology. The work is taking place from approximately July to early October.
“This will displace some of our board and commission meetings, as well as a few City Council meetings, so we are exploring alternative locations, including with SUSD. I’m not aware of displacing any staff during the work,” Peralta added.
The site at 7501 E. Oak St. was originally Tonto Elementary, which was repurposed after the school closed.
Earlier in March, in what Menzel called “a win-win in the partnership with the city,” the district board approved a contract for the city to pay SUSD $15,000 per month for a building at 7501 E. Oak St.
According to the SUSD agenda, “The city desires to use the district’s property located at 7501 E. Oak Street for the relocation of city staff, operation of municipal services, staff and visitor parking, and activity reasonably related to the operation of municipal governmental functions for a two year period of time.”
The lease agreement provides for an option to renew for up to two additional one-year terms.
“We learned of (the city’s) interest due to significant renovation going on at some of their facilities,” Menzel told the board.
The board unanimously approved the agreement.